The feasibility study for the fast railroad line along the north-south Corridor 10 will be completed this summer, and then followed by a review, said Deputy Prime Minister Aleksandar Nikoloski.
The planning process must end perfectly. The initial deadline I stated, that the project will be completed by 2031, remains, and nothing has been changed, said Deputy Prime Minister Aleksandar Nikoloski.
As Nikoloski pointed out in response to media questions, activities that are extremely important, even the most significant for the entire project, are underway, but they are not sufficiently visible and interesting to the public. The project began in October last year, and construction activities include geotechnical surveys.
Considering that the request, both from us and the bank that will fund the project, will be that the deadline for completion is five years, there will be no compromises, because the penalties for the contractor will be very high if they break the deadline, said Nikoloski, who is also Transportation Minister who is negotiating the deal as part of the strategic partnership treaty with the UK.
The first phase is to secure financing, the second is to do good planning and the third is to carry it out on the ground. In terms of financing, the work was completed last year, an indicative offer was selected, which, of course, when the planning process is completed, which is the second phase, should be confirmed. That process was completed last year. In terms of planning, in my opinion the most important and significant part, considering that we will be working on this project with Great Britain, the documentation and what was previously done as planning with the European Union, was considered insufficient for the implementation of such a large infrastructure project and therefore we entered a completely new planning process, which includes many phases. Nine routes were offered, one was chosen. It is clear what the route is, it more or less follows the existing line, but eight other options were offered. The second is an environmental impact assessment based on the route that was chosen. The third is an assessment of the impact on the social environment. The fourth is for the protection of cultural and historical heritage, taking into account that there are at least two large sites on the route, Stobi and Vardarski Rid. The fifth is a preliminary design or projection, the sixth is geotechnical investigations and the seventh is the project, said Nikoloski.
According to him, due diligence analysis and feasibility study are being done side by side, which should incorporate all these activities.
The post Nikoloski: feasibility study on the Corridor 10 fast railroad will be finished this summer appeared first on Republika English.
Nikoloski: feasibility study on the Corridor 10 fast railroad will be finished this summer 2026 IUSTITIA.BG – Investigations 2009-2025 2026-05-14 20:59:53 Latest news World news Country news Most important news latest news most important latest of the day Justice Petar Nizamov Feathers Petar Nizamov- Feathers Justice bg iustitia.bg iustitia iusticia usticia investigation Burgas Bulgaria news news of the last hour news of the day news of today Bulgaria news The news from Bulgaria blitz news top news most important most commented latest news Boyko Borisov news weather coronavirus news news weather facebook youtube facebook instagram news today news of the last minutes news today today news news bg news leading news hot news bg news site for news all news news bg news of the last hour latest latest news bg news of today news today news today news of the last hour latest news today news bg news news 24 hours news vesti bg novini news world bird bg bivol bg bivol trud bg novini latest news today novinite bg news hello bulgaria political party coat of arms delyan peevski scandalous Bulgarian National Television Free Europe Television scandal exclusive live tv live right now tv tv online tv program bg live now tv news online tv online live court Burgas court Burgas district court Burgas court Burgas district court Burgas district court Burgas appellate court Burgas prosecutor Burgas prosecutor’s office Burgas district prosecutor’s office Burgas district prosecutor’s office Burgas district prosecutor’s office Burgas district prosecutor’s office Burgas district prosecutor’s office Burgas district prosecutor’s office Prosecutor General Ivan Geshev Prosecutor Geshev Tsatsarov Ministry of Internal Affairs Burgas ODMR Burgas ODPR Burgas police Burgas district police Burgas prosecutor Tsatsarov SGS cases Varna court chairman of the SGS court decisions on civil cases decisions on cases Plovdiv court decision of the court decisions cases Varna court criminal cases district district court decisions work in the court SGS chairman of the SGS judges Sofia court post judges Plovdiv court Plovdiv judges Plovdiv Supreme Court Inspectorate Supreme Court Supreme Judicial Council lawyer lawyer criminal cases lawyer civil cases lawyer marriage cases lawyer administrative criminal law criminal process civil law civil process administrative law constitutional law